Construction of 3000m^2 Loffelstein retaining wall at the cut face of Mpilo Boulevard

The project is implemented by the Maseru City Council.

The project started in November 2010 and the planned completion date was April 2011. The project could not be completed at the planned completion date due to heavy rains received in December 2010, January 2011 and February 2011 and relocation of affected properties, therefore extension of time was granted till the end of June 2011

Construction of 3000m2 Loffelstein retaining wall at the cut face of Mpilo Boulevard.